Chesterwell Co-Op

Feb, 2022

CASE STUDY

Chesterwell Co-Op

SERVICES

Electrical

CONTRACTOR

Ceetech

DATE

Feb, 2022

OVERVIEW

Chesterwell is a new community of 1600 homes in north Colchester. A Co-Op premium format store, with a barista bar, opened in December 2021 after a twelve-month construction period.

Ceetech were engaged in October for the project management, design and installation of electrical work for refrigeration cases, and CCTV and security systems.

The deadline for completion was fully committed with no room for delays, at a time when supply chains were struggling and once again COVID-19 was on the increase. To manage this, supplies were ordered immediately and held in stock to ensure no delay was experienced. Extra resources were placed on the project at early stages to get ahead and fast track.

Project

Our Health and Safety standards on site remained paramount and were commented on by our Health and Safety Advisor as good throughout the project.

Ceetech has industry recognition for our Training and Development. Our Apprentices installed a large amount of the cable tray, with close supervision from the electrical foreman. We were able to invite the college onto the site to witness the fantastic work the apprentices were doing.

Ceetech has a proven track record with the Co-Op and a strong client relationship, resulting in Ceetech being trusted to deliver high quality work on time.

The store was officially opened at the beginning of December 2021 as planned, ready for the Christmas trade.

Result